Earned Value Management
Earned Value Management (EVM) is a project management technique used to assess a project's progress in terms of cost and schedule. It integrates data on scope, schedule, and cost to give project managers a comprehensive view of project performance. Here's how it works:
Planned Value (PV): This is the authorized budget assigned to scheduled work. It represents the estimated value of the work scheduled to be completed by a specific time.
Earned Value (EV): This is the value of the work actually performed. It represents the budgeted cost of the work that has actually been completed at a specific point in time.
Actual Cost (AC): This is the total cost actually incurred (Money spent) and recorded in accomplishing the work performed for a specific time period.
With these three values, several performance metrics can be calculated:
Cost Performance Index (CPI): This is the ratio of earned value to actual cost. It indicates how efficiently the project is using its budget. A CPI greater than 1 indicates under budget, while less than 1 indicates over budget.
Schedule Performance Index (SPI): This is the ratio of earned value to planned value. It indicates how efficiently the project is progressing in terms of schedule. An SPI greater than 1 indicates ahead of schedule, while less than 1 indicates behind schedule.
Variance Analysis: By comparing the planned, earned, and actual values, variances can be calculated. Positive variances indicate that the project is performing better than planned, while negative variances indicate the opposite.
Estimate at Completion (EAC): This is a forecasted total cost of the project based on performance to date. It can be calculated using various methods, such as dividing the budget at completion by the cost performance index.
To Complete Performance Index (TCPI): This is the projected efficiency needed to complete the remaining work within the original budget. It can be calculated using various methods, such as dividing the remaining work by the remaining budget.
EVM provides project managers with valuable insights into project performance, allowing them to identify issues early, make informed decisions, and take corrective actions to keep the project on track. It is widely used in industries such as construction, engineering, and software development where projects are complex and involve significant costs and timelines.
Schedule and Cost Variance
Schedule variance (SV) is another metric used in earned value management (EVM) to measure the difference between the earned value (EV) and the planned value (PV) of work performed up to a certain point in time. A positive SV indicates that the project is ahead of schedule, while a negative SV indicates that the project is behind schedule.
Let's take construction project example:
Suppose the same construction project has progressed further, and you gather the following additional data:
- Planned Value (PV): $500,000
- Earned Value (EV): $480,000
To calculate the schedule variance (SV), you would use the formula:
SV=EV−PV
Substitute the values into the formula:
EV=480,000−500,000SV=480,000−500,000
EV=−20,000SV=−20,000
So, the schedule variance for the project at this point is -$20,000. This means that the project has completed $20,000 less work than planned according to the project schedule. It indicates that the project is behind schedule, requiring attention from the project manager to analyze the causes of the delay and take necessary corrective actions to get the project back on track in terms of schedule.
Cost variance (CV) is a measure in earned value management (EVM) that indicates the difference between the earned value (EV) and the actual cost (AC) of work performed up to a certain point in time. A positive CV indicates that the project is under budget, while a negative CV indicates that the project is over budget.
Let's consider an example:
Suppose you are managing a construction project to build a new office building. The total budget for the project is $1,000,000. After completing the first phase of the project, you gather the following data:
- Planned Value (PV): $200,000
- Earned Value (EV): $180,000
- Actual Cost (AC): $190,000
To calculate the cost variance (CV), you would use the formula:
CV=EV−AC
Substitute the values into the formula:
CV=180,000−190,000CV=180,000−190,000
CV=−10,000
So, the cost variance for the project at this point is -$10,000. This means that the project has spent $10,000 more than the value of the work completed according to the project plan. It indicates a cost overrun, which would require attention from the project manager to analyze the reasons for the variance and take appropriate corrective actions to bring the project back on track financially.
CPI and SPI
Let's continue with the construction project example to demonstrate how to calculate the Schedule Performance Index (SPI) and the Cost Performance Index (CPI).
Suppose the project progresses further, and you gather the following additional data:
- Planned Value (PV): $600,000
- Earned Value (EV): $550,000
- Actual Cost (AC): $600,000
To calculate the Schedule Performance Index (SPI), you would use the formula:
SPI= EV/PV
Substitute the values into the formula:
SPI = 550,000/600,000,
SPI≈0.917
So, the Schedule Performance Index (SPI) for the project at this point is approximately 0.917. This indicates that for every dollar planned to be spent, the project has earned approximately $0.917 worth of work. Since SPI < 1, it means the project is behind schedule.
Now, let's calculate the Cost Performance Index (CPI).
To calculate the Cost Performance Index (CPI), you would use the formula:
CPI= EV/AC
Substitute the values into the formula:
CPI=550,000/600,000
CPI≈0.917
So, the Cost Performance Index (CPI) for the project at this point is approximately 0.917. This means that for every dollar spent, the project has earned approximately $0.917 worth of work. Since CPI < 1, it indicates that the project is over budget.
In summary:
- SPI < 1 indicates the project is behind schedule.
- CPI < 1 indicates the project is over budget.
Both SPI and CPI provide crucial insights into project performance, helping project managers identify areas that require attention and take necessary corrective actions to keep the project on track.
EAC , ETC And VAC
Let's continue with the construction project example to demonstrate how to calculate Estimate at Completion (EAC), Estimate to Complete (ETC), and Variance at Completion (VAC).
Suppose the project progresses further, and you gather the following additional data:
- Planned Value (PV): $600,000
- Earned Value (EV): $550,000
- Actual Cost (AC): $700,000
- BAC = $ 1000000
We've already calculated CPI as $550,000 / $700,000 ≈ 0.786. Now, we can use this CPI to calculate EAC and ETC.
Estimate at Completion (EAC)
There are various methods to calculate EAC. One common method is using the cost performance index (CPI) to forecast the final project cost. The formula used here is:
EAC= BAC/CPI
Where:
- BAC is the Budget at Completion, which is the total budget for the project.
- CPI is the Cost Performance Index.
Substitute the values into the formula: EAC =1,000,0000/.786
EAC≈1,272,727
So, the Estimate at Completion (EAC) for the project using CPI is approximately $1,272,727.
Estimate to Complete (ETC)
The Estimate to Complete (ETC) is the forecasted cost needed to complete the remaining work. It can be calculated using the formula:
ETC=EAC−AC
Substitute the values into the formula: ETC=1,272,727−700,000
ETC≈572,727
So, the Estimate to Complete (ETC) for the project is approximately $572,727.
Variance at Completion (VAC)
Variance at Completion (VAC) represents the difference between the budget at completion (BAC) and the Estimate at Completion (EAC). The formula is:
VAC=BAC−EAC
Substitute the values into the formula: VAC=1,000,000−1,272,727
VAC≈−272,727
So, the Variance at Completion (VAC) for the project is approximately -$272,727. A negative VAC indicates that the project is expected to overrun its budget by that amount based on the current performance.
The forecasting formula used above are to assess the baseline performance with the current CPI and SPI. We can use the following formulas if the work remaining is done at a different CPI or SPI.
EAC = AC + (BAC-EV)/CPI If the work remaining is done at a different value of CPI
EAC = AC + (BAC-EV) If the work remaining is done at a budgeted rate
EAC = AC + (BAC-EV)/CPI X SPI If the work remaining is done at a different CPI and SPI
EAC = AC + ETC (Bottom up) Re-estimate the remaining work using bottom up estimation
To Complete Performance Index (TCPI)
To illustrate the To Complete Performance Index (TCPI) concept, let's consider an example scenario:
Suppose you're managing a software development project with the following data:
- Budget at Completion (BAC): $100,000
- Earned Value (EV): $50,000
- Actual Cost (AC): $60,000
- Estimate at Completion (EAC): $120,000
Example 1: TCPI to Achieve Original Budget (BAC)
We want to calculate the TCPI needed to achieve the original budget (BAC) of $100,000.
TCPI=To illustrate the To Complete Performance Index (TCPI) concept, let's consider an example scenario:
Suppose you're managing a software development project with the following data:
- Budget at Completion (BAC): $100,000
- Earned Value (EV): $50,000
- Actual Cost (AC): $60,000
- Estimate at Completion (EAC): $120,000
Example 1: TCPI to Achieve Original Budget (BAC)
We want to calculate the TCPI needed to achieve the original budget (BAC) of $100,000.
TCPI=(BAC−EV)/(BAC−AC)
Substitute the given values into the formula:
TCPI=(100,000−50,000)/(100,000−60,000)
TCPI=50,000/4,0000
TCPI=1.25
So, the TCPI needed to achieve the original budget (BAC) is 1.25. This means that to complete the project within the original budget, the project team need to be 25% more efficient than they have been so far.
Example 2: TCPI with EAC
We want to calculate the TCPI needed to achieve the Estimate at Completion (EAC) of $120,000.
TCPI= (BAC−EV)/(EAC−AC)
Substitute the given values into the formula:
TCPI =(100,000−50,000)/(120,000−60,000) = 50000/60000
TCPI≈0.83
So, the TCPI needed to achieve the Estimate at Completion (EAC) of $120,000 is approximately 0.83. This means that the project with the revised budget, even if the project teamwork at 83% efficiency they will achieve the target.
These examples demonstrate how TCPI can be used to assess the performance efficiency required to achieve specific project goals, whether it's staying within the original budget or meeting a revised budget estimate.

20 Multiple-Choice Questions (MCQs) on Earned Value Management (EVM)
1. What is the primary purpose of Earned Value Management (EVM)?
a) To track employee productivity
b) To monitor project performance in terms of scope, schedule, and cost
c) To identify project risks
d) To increase project complexity
✅ Answer: b
📌 Explanation: EVM helps project managers analyze project performance by integrating scope, schedule, and cost metrics.
2. What does Planned Value (PV) represent in EVM?
a) The actual cost incurred so far
b) The approved budget for work planned to be completed
c) The total project budget
d) The value of completed work
✅ Answer: b
📌 Explanation: Planned Value (PV) is the budgeted cost for the work planned to be completed at a given point in time.
3. Earned Value (EV) is defined as:
a) The budgeted cost of work performed
b) The actual cost of work performed
c) The total project cost
d) The estimated cost at project completion
✅ Answer: a
📌 Explanation: EV represents the budgeted cost of work actually completed at a given time.
4. Actual Cost (AC) in EVM refers to:
a) The planned expenditure
b) The actual money spent on completed work
c) The total project budget
d) The estimated cost for future work
✅ Answer: b
📌 Explanation: AC is the actual amount spent on work completed up to a specific point.
5. Which formula is used to calculate Cost Variance (CV)?
a) CV = EV - AC
b) CV = PV - EV
c) CV = AC - EV
d) CV = PV - AC
✅ Answer: a
📌 Explanation: Cost Variance (CV) indicates cost performance by comparing earned value (EV) with actual cost (AC).
6. A negative Cost Variance (CV) indicates that the project is:
a) Over budget
b) Under budget
c) Ahead of schedule
d) Behind schedule
✅ Answer: a
📌 Explanation: A negative CV (CV < 0) means that the actual costs (AC) exceed the earned value (EV), indicating the project is over budget.
7. Schedule Variance (SV) is calculated using which formula?
a) SV = EV - PV
b) SV = PV - EV
c) SV = AC - EV
d) SV = EV - AC
✅ Answer: a
📌 Explanation: Schedule Variance (SV) measures the difference between work completed (EV) and work planned (PV).
8. If SV is negative, it means the project is:
a) Ahead of schedule
b) Behind schedule
c) Under budget
d) Over budget
✅ Answer: b
📌 Explanation: A negative SV (SV < 0) means that less work has been completed than planned, indicating the project is behind schedule.
9. Cost Performance Index (CPI) is calculated using which formula?
a) CPI = EV / AC
b) CPI = AC / EV
c) CPI = PV / EV
d) CPI = EV / PV
✅ Answer: a
📌 Explanation: CPI measures cost efficiency by comparing earned value (EV) with actual cost (AC).
10. A CPI greater than 1.0 means the project is:
a) Over budget
b) Under budget
c) Behind schedule
d) Ahead of schedule
✅ Answer: b
📌 Explanation: CPI > 1.0 means the project is cost-efficient, as it is spending less than planned for the work completed.
11. Schedule Performance Index (SPI) is calculated as:
a) SPI = EV / PV
b) SPI = PV / EV
c) SPI = EV / AC
d) SPI = AC / EV
✅ Answer: a
📌 Explanation: SPI measures schedule efficiency by comparing earned value (EV) with planned value (PV).
12. If SPI is less than 1.0, the project is:
a) Behind schedule
b) Ahead of schedule
c) On budget
d) Under budget
✅ Answer: a
📌 Explanation: SPI < 1.0 means that work is progressing slower than planned, indicating schedule delays.
13. The Estimate at Completion (EAC) formula when current cost performance continues is:
a) EAC = BAC / CPI
b) EAC = BAC × CPI
c) EAC = BAC - CPI
d) EAC = BAC + CPI
✅ Answer: a
📌 Explanation: EAC = BAC / CPI predicts the total project cost based on current cost efficiency trends.
14. Variance at Completion (VAC) is calculated as:
a) VAC = BAC - EAC
b) VAC = EAC - BAC
c) VAC = BAC / EAC
d) VAC = BAC × CPI
✅ Answer: a
📌 Explanation: VAC estimates how much the project will be over or under budget at completion.
15. What does an SPI of 1.2 indicate?
a) The project is behind schedule
b) The project is ahead of schedule
c) The project is over budget
d) The project is under budget
✅ Answer: b
📌 Explanation: SPI > 1.0 means the project is progressing faster than planned.
16. The Estimate to Complete (ETC) formula is:
a) ETC = EAC - AC
b) ETC = BAC - EV
c) ETC = BAC / CPI
d) ETC = PV - EV
✅ Answer: a
📌 Explanation: ETC estimates the remaining cost needed to complete the project.
17. Which of the following is an advantage of EVM?
a) Provides a real-time snapshot of project health
b) Eliminates project risks
c) Guarantees project success
d) Prevents scope changes
✅ Answer: a
📌 Explanation: EVM helps monitor and control project progress, allowing for timely corrective actions.
18. What does a CPI of 0.85 indicate?
a) The project is over budget
b) The project is under budget
c) The project is ahead of schedule
d) The project is on budget
✅ Answer: a
📌 Explanation: CPI < 1.0 means the project is cost-inefficient and over budget.
19. What is the Budget at Completion (BAC)?
a) The total planned project budget
b) The actual cost spent so far
c) The earned value of completed work
d) The remaining project cost
✅ Answer: a
📌 Explanation: BAC represents the original approved total budget for the project.
20. A CPI of 1.0 means:
a) The project is under budget
b) The project is on budget
c) The project is over budget
d) The project is ahead of schedule
✅ Answer: b
📌 Explanation: CPI = 1.0 means the project is spending exactly as planned.

Multiple-choice questions (MCQs) on Earned Value Management (EVM)
1. You are managing a project with a budget of $100,000 and it is expected to last 10 months. After 4 months, $45,000 has been spent and 40% of the work is completed. What is the Cost Performance Index (CPI)?
A. 0.89
B. 0.80
C. 1.11
D. 1.25
Answer: A. 0.89
Explanation:
-
EV (Earned Value) = 40% of $100,000 = $40,000
-
AC (Actual Cost) = $45,000
-
CPI = EV / AC = $40,000 / $45,000 = 0.89
Correction: The correct CPI is 0.89.
✅ Correct answer: A. 0.89
2. If the SPI (Schedule Performance Index) is 0.75 and CPI (Cost Performance Index) is 1.10, what does this indicate about the project?
A. The project is ahead of schedule and over budget
B. The project is behind schedule and under budget
C. The project is ahead of schedule and under budget
D. The project is behind schedule and over budget
Answer: B. The project is behind schedule and under budget
Explanation:
-
SPI < 1.0 → behind schedule
-
CPI > 1.0 → under budget
3. Which formula represents the Estimate at Completion (EAC) assuming current cost performance will continue?
A. EAC = BAC / CPI
B. EAC = AC + (BAC – EV)
C. EAC = AC + ETC
D. EAC = BAC / SPI
Answer: A. EAC = BAC / CPI
Explanation:
This formula is used when the current cost performance is expected to continue.
4. The project has a BAC (Budget at Completion) of $200,000. The EV is $100,000 and the AC is $120,000. What is the Variance at Completion (VAC)?
A. -$40,000
B. $20,000
C. $100,000
D. -$100,000
Answer: A. -$40,000
Explanation:
First, find EAC using:
EAC = BAC / CPI = 200,000 / (100,000 / 120,000) = 200,000 / 0.8333 ≈ $240,000
VAC = BAC – EAC = 200,000 – 240,000 = –$40,000
5. If the Earned Value (EV) = $90,000, Actual Cost (AC) = $100,000, and Planned Value (PV) = $120,000, what are the CPI and SPI?
A. CPI = 0.90, SPI = 0.75
B. CPI = 1.11, SPI = 0.80
C. CPI = 0.75, SPI = 0.90
D. CPI = 0.90, SPI = 0.75
Answer: D. CPI = 0.90, SPI = 0.75
Explanation:
-
CPI = EV / AC = 90,000 / 100,000 = 0.90
-
SPI = EV / PV = 90,000 / 120,000 = 0.75
6. A project has the following data: EV = $150,000, AC = $170,000, PV = $160,000. What are the CV and SV?
A. CV = -$20,000; SV = -$10,000
B. CV = $20,000; SV = -$10,000
C. CV = -$20,000; SV = $10,000
D. CV = $20,000; SV = $10,000
Answer: A. CV = -$20,000; SV = -$10,000
Explanation:
-
CV = EV – AC = 150,000 – 170,000 = –$20,000
-
SV = EV – PV = 150,000 – 160,000 = –$10,000
→ Negative values indicate the project is over budget and behind schedule.
7. What does a Cost Variance (CV) greater than zero indicate?
A. Project is under budget
B. Project is over budget
C. Project is ahead of schedule
D. Project is behind schedule
Answer: A. Project is under budget
Explanation:
CV = EV – AC
-
If CV > 0, Earned Value > Actual Cost → you're spending less than planned → under budget.
8. You are reviewing a project with SPI = 1.2 and CPI = 0.85. What is the status?
A. Ahead of schedule, under budget
B. Ahead of schedule, over budget
C. Behind schedule, under budget
D. Behind schedule, over budget
Answer: B. Ahead of schedule, over budget
Explanation:
-
SPI > 1 → ahead of schedule
-
CPI < 1 → over budget
9. If Earned Value (EV) = $50,000 and Actual Cost (AC) = $50,000, what is the CPI?
A. 0
B. 1.0
C. 2.0
D. Cannot be determined
Answer: B. 1.0
Explanation:
CPI = EV / AC = 50,000 / 50,000 = 1.0 → Project is exactly on budget.
10. A project has PV = $100,000, EV = $80,000, and AC = $90,000. What are CPI and SPI?
A. CPI = 0.89, SPI = 0.80
B. CPI = 1.13, SPI = 0.89
C. CPI = 0.80, SPI = 0.89
D. CPI = 0.89, SPI = 1.13
Answer: A. CPI = 0.89, SPI = 0.80
Explanation:
-
CPI = EV / AC = 80,000 / 90,000 = 0.89
-
SPI = EV / PV = 80,000 / 100,000 = 0.80
11. In which case is the project both behind schedule and under budget?
A. SPI < 1 and CPI > 1
B. SPI > 1 and CPI < 1
C. SPI < 1 and CPI < 1
D. SPI > 1 and CPI > 1
Answer: A. SPI < 1 and CPI > 1
Explanation:
-
SPI < 1 → behind schedule
-
CPI > 1 → under budget
12. What is the interpretation of a Schedule Variance (SV) equal to zero?
A. The project is behind schedule
B. The project is on schedule
C. The project is ahead of schedule
D. The project is on budget
Answer: B. The project is on schedule
Explanation:
SV = EV – PV
-
If SV = 0 → work accomplished = work planned → on schedule
13. A project has the following data: BAC = $500,000, EV = $300,000, AC = $350,000. What is the Estimate at Completion (EAC), assuming current cost performance continues?
A. $500,000
B. $583,333
C. $550,000
D. $600,000
Answer: B. $583,333
Explanation:
Use formula:
EAC = BAC / CPI, where CPI = EV / AC
→ CPI = 300,000 / 350,000 = 0.857
→ EAC = 500,000 / 0.857 ≈ $583,333
14. If EAC = $480,000 and BAC = $500,000, what is the Variance at Completion (VAC)?
A. $20,000
B. -$20,000
C. $80,000
D. -$80,000
Answer: A. $20,000
Explanation:
VAC = BAC – EAC = 500,000 – 480,000 = $20,000
Positive VAC means the project is forecasted to be under budget.
15. A project has AC = $200,000 and EV = $180,000. You estimate that the remaining work will cost $250,000. What is the EAC using the formula: EAC = AC + ETC?
A. $380,000
B. $430,000
C. $450,000
D. $470,000
Answer: B. $430,000
Explanation:
EAC = AC + ETC = 200,000 + 250,000 = $430,000
16. You are given: BAC = $300,000, EV = $150,000, and AC = $180,000. If the project team believes future cost performance will differ, and the remaining work is estimated to cost $120,000, what is the new EAC?
A. $300,000
B. $330,000
C. $270,000
D. $250,000
Answer: A. $300,000
Explanation:
EAC = AC + new ETC = 180,000 + 120,000 = $300,000
(This method is used when future cost performance is expected to differ from current performance.)
17. Which formula is used for EAC when the initial plan is no longer valid?
A. EAC = BAC / CPI
B. EAC = AC + ETC (new estimate)
C. EAC = AC + (BAC – EV)
D. EAC = AC + (BAC – EV) / (CPI × SPI)
Answer: B. EAC = AC + ETC (new estimate)
Explanation:
This is used when future work is re-estimated, and past performance is not expected to repeat.
18. What does a negative VAC indicate?
A. The project is ahead of schedule
B. The project is under budget
C. The project is over budget
D. The project is behind schedule
Answer: C. The project is over budget
Explanation:
VAC = BAC – EAC
If VAC < 0 → EAC > BAC → Over budget
19. A project has BAC = $1,000,000, EV = $500,000, AC = $600,000. Assuming the cost performance will continue, what is EAC?
A. $1,000,000
B. $1,200,000
C. $1,100,000
D. $900,000
Answer: B. $1,200,000
Explanation:
CPI = EV / AC = 500,000 / 600,000 = 0.833
EAC = BAC / CPI = 1,000,000 / 0.833 ≈ $1,200,000
20. If the current SPI is 0.95 and the CPI is 1.0, what is the implication?
A. The project is ahead of schedule and on budget
B. The project is behind schedule and over budget
C. The project is behind schedule and on budget
D. The project is on schedule and under budget
Answer: C. The project is behind schedule and on budget
Explanation:
-
SPI < 1 → behind schedule
-
CPI = 1 → on budget

